CHAPTER XIX.
THE GENESEE VALLEY CANAL.
Including the Dansville branch, the extension to Millgrove, and the various feeders and reservoirs, from the inception of the
project to the abandonment of the canal.
------------------------------------------------------------------------
The year 1825 marked a new era in the internal navigation of New York
State. New York City now had direct water communication both with the
Great Lakes and with Lake Champlain by means of the Erie and
Champlain canals. The next step was by a system of branch or lateral
canals, to connect the inland portions of the state with these main
waterways.
The prosperity which had followed the opening of the Erie, section by
section, and the rapidity with which the glowing predictions of early
promoters were being realized led to a veritable canal mania. From
all parts of the state came the cry for a share in the benefits of
internal navigation, and the Legislatures were flooded with petitions
which, if acceded to, would have covered the state with a network of
canals.
In the western section of the state, in the valley of the Genesee
river, was an extensive tract of wonderfully fertile and productive
land, having no means of access to the markets of the country. The
Genesee river, which meets the Erie canal at Rochester, is separated
from the Allegheny river at Olean by a very narrow divide. By
constructing a canal across this divide and by canalizing the two
rivers, an unbroken inland water communication would be afforded
between all the important sections of New York State and the valleys
of the Ohio, Mississippi, Missouri. Arkansas, Osage, Illinois,
Wabash, Tennessee and Cumberland rivers, three-quarters of the entire
territory of the United States. The dream of so extensive a line of
internal communication appealed to the people of the Genesee valley
as affording irresistible arguments for constructing a canal along
this route. As early as 1823 a petition from citizens of the counties
of Monroe, Livingston, Genesee, Allegany and Cattaraugus was
presented to the State Legislature praying for an appropriation of
$10,000 from the State treasury for the purpose of improving the
navigation of the Genesee river. This petition, however, had no
immediate results.
This route was not considered to be of sufficient importance or else
its advocates were not insistent enough to have it included in the
first group of lateral canals that were authorized, but it was begun
after the mania for canal-building had somewhat abated, after the
utility of railroads began to be demonstrated, and its construction
was protracted during a long period while the resources of the State
were being severely taxed for the enlargement and repairs of the
other canals. The whole history of this canal reveals a series of
unfortunate events; the numerous delays were very costly; the time
for building, most inauspicious; and even the advisability of
beginning the project at so late a day is not sustained by results.
The subject first came before the Legislature for serious
consideration as the result of a message of Governor De Witt Clinton
in February, 1825, "respecting a navigable communication between the
waters of the Allegany river and the Erie canal, and soliciting a
full investigation of the proposed measure by able engineers" 1 and
recommending the adoption of effectual preliminary measures.
As a result of this message, together with sixteen petitions from
counties in the neighborhood of the proposed improvement, an act was
passed on April 20, 1825, rendering it "the duty of the canal
commissioners to cause examinations, surveys and estimates to be made
of the most eligible routes . . . from Rochester to Allegany river at
Olean, through the valley of Genesee river; from Scottsville by way
of Le Roy, to the upper falls of the Genesee river; . . . from Lake
Erie to Allegany river, through the valley of the Conawanga, and from
the Allegany river at Olean to the Erie canal by way of the village
of Batavia." 2 In accordance with this law the canal commissioners in
1826 reported the practicability of each of these routes, although
they did not endeavor to make any comparisons between them.
This act of 1825 showed to what an extent this desire to participate
in the benefits of canal navigation had spread throughout the state.
The act ordered the surveys of seventeen separate routes in various
parts of the state. James Geddes, the veteran engineer of the Erie
canal, made the surveys, and his reports were embodied in the
communications from the canal commissioners. Although twenty-nine
petitions were presented during the spring of 1826, no legislation
was enacted concerning this project. In 1827 fifteen petitions were
presented, some praying for the construction of a canal from the Erie
canal by the way of Tonawanda creek to the Allegheny river at Olean;
some by the Genesee valley route, and others for a canal from the
Erie canal at Buffalo to the Allegheny river along the valley of the
Conewango creek. The canal committee to which these petitions were
referred could not select a line from the rough surveys already made
of the three routes, and recommended that for the present the
condition of the finances of the State was not such as to warrant the
expense of constructing this canal.
In April, 1827, an act was passed incorporating a company to improve
the navigation of the Cassedaga and Conewango creeks and the
Chautauqua outlet. Although incorporated for the purpose of
constructing the long desired canal, this company accomplished
nothing. During the next three years twenty-seven petitions were
received. In April, 1830, an act was finally passed authorizing a
careful survey of the Genesee valley route, but as the appropriation
($750) was so obviously inadequate, no survey was attempted.
From 1831 to 1833, only nineteen petitions were presented, but in
1834 the friends of the Genesee valley route began work in earnest
and twenty-eight petitions were brought before the Legislature. The
desire for the canal was no longer confined to the counties in the
western part of the state, but from every section came petitions.
Even the common council of the City of New York and the American
Institute of the City of New York passed resolutions "appealing to
the intelligence, justice and patriotism of the Legislature" to
effect the necessary legislation for the opening of intercourse with
Pittsburg and the inexhaustible beds of bituminous coal of western
Pennsylvania by means of the canal system of the State. The valley
through which this proposed canal was to pass contained over one
hundred thousand inhabitants and remarkably fertile lands. Annually
over 200,000,000 feet of lumber passed down the Allegheny river, and
it was supposed that this would, for the most part, be deflected to
the New York State canals. From these considerations the canal
committee recommended a minute survey of the Genesee valley route. An
act to this effect was passed on April 30, 1834, and it also provided
for a side-cut from the village of Dansville down the Canaseraga
creek to the Genesee valley line at or near Mount Morris.
In compliance with instructions received from the canal commissioners
a very complete survey and examination of the proposed route was made
by an engineer, Mr. Frederick C. Mills, the result of whose
investigations was embodied in the report of the canal commissioners
on March 2, 1835. Mr. Mills reported that the proposed canal, side-
cut and navigable feeders, if located on the west side of the Genesee
river, would extend over 122 ¼ miles, with 1,057 feet of lockage and
were estimated to cost $1,890,614.12; if the east side of the river
were chosen, the length would be 123 3/10 miles, the amount of
lockage the same, and the estimated cost, $2,002,285.92. These
estimates did not take into consideration damages to lands through
which the canal was to pass or to hydraulic works and water-
privileges. A part of the line south of Mount Morris was shown to be
very difficult and expensive. At the falls, the high lands closed in
upon the river with perpendicular sides, at some places rising nearly
four hundred feet. In a distance of two miles the river appeared to
be a continuous succession of falls, descending two hundred and
seventy-four feet. The plan proposed was to construct a tunnel for
one thousand and fifty-six feet through an immense projecting cliff
of rock. The summit level of this canal was to be eleven and a half
miles long and the greatest depth of excavation was stated at twelve
feet. It was estimated that an adequate supply of water could be
obtained without any material damage to water-privileges.
This report was made too late in the year for any action to be taken
on it, but the friends of the project were determined that by
persevering they would win, and during the sessions of 1835-6 one
hundred and eleven petitions were filed. Finally, on the 6th of May,
1836, an act was passed (chapter 257), providing for the construction
of a navigable canal, to be known as the Genesee Valley canal, "from
the Erie canal in the city of Rochester, through the valley of the
Genesee river, to a point at or near Mount-Morris; and from thence,
by the most eligible route, to the Allegany river, at or near Olean;
and also a branch of the same, commencing at or near Mount-Morris,
and extending up the valley of the Canaseraga creek, at or near the
village of Dansville. And should the canal commissioners be of the
opinion that the construction of the said canal will injure the
hydraulic privileges at Rochester, then they are required to connect
the said canal with the Genesee river, above the feeder dam above
Rochester, and from thence to construct a navigable canal to the Erie
canal, or improve the Erie canal feeder from this place, as may best
promote the public interest.
"The canal commissioners shall determine on the width and depth of
the said canal and branch . . . and shall borrow, on the credit of
the state, . . . such sum or sums of money as shall be required for
the same, as they shall deem best for the interest of the state, not
exceeding two millions of dollars." 3
In June, 1837, contracts were let for building that portion of the
canal extending from the Erie canal in Rochester to the rapids on the
Genesee river, a distance of two miles. The estimated cost of these
two miles of canal, including the expense of a dam across the Genesee
river, was $47,492.59. On the fourteenth of November, 1837, proposals
were received for constructing twenty-eight miles of this canal from
the rapids to Piffard’s in the county of Livingston. The cost of the
work calculated at contract prices was $522,181.89, while the
estimate of 1834 was only $408,725.63, but the prices of supplies of
all kinds, were considerably higher than when the first estimate was
made.
At Scottsville the Genesee Valley canal crossed that of the
Scottsville Canal Company, a company that was organized in 1829, with
a capital of $15,000 to build a canal from Scottsville to the Genesee
river.
By January 1, 1839, the first two miles of the Genesee Valley canal
were completed and work was in progress on fifty-one miles more, from
the rapids to Dansville, all of this work to be completed, according
to the terms of contracts, by October 1, 1840. In addition, the canal
commissioners had made a careful examination of the various proposed
routes from Mount Morris to the Allegheny river, and after having
finally decided on a route, contracts for fifty miles had been let on
October 31, 1838. This route passed from Mount Morris up the valley
of the Canaseraga creek to the Keshequa creek, following the line on
which the branch canal to Dansville had been located; thence up the
valley of that stream through the village of Nunda and Messenger’s
hollow, by the deep cut near Colonel William’s, and thence to the
Genesee river, crossing that stream by an aqueduct to Portageville;
thence up the west side of the river to Black creek; thence up the
valley of that stream to Cuba; thence down on the east side of Oil
creek to Hinsdale; thence down on the east side of Olean creek to
near the village of Olean, crossing that creek by an aqueduct, and
thence passing the village of Olean to the Allegheny river. The work
under contract at that time between Rochester and the village of
Nunda called for an expenditure of $1,959,011, while the estimated
cost of completing the canal between Nunda and the Allegheny river
amounted to an additional sum of $2,791,111.79. These contracts and
plans called for a canal twenty-six feet wide on the bottom, forty-
two feet wide at water-surface, the banks seven feet high and
calculated for four feet of water, the locks to be built of hammer-
dressed masonry, laid in hydraulic cement, ninety feet long and
fifteen feet wide.
In May, 1839, an act (chapter 305) was passed favoring a cheaper form
of lock and giving the canal commissioners the power to change the
plans accordingly, thereby reducing the expense of the canal
$384,506.95. The contracts for the remaining twenty miles were let in
October, 1839.
That portion of the Genesee Valley canal between its intersection
with the Erie canal at Rochester and the Genesee river dam near Mount
Morris, a distance of thirty-six miles, was so far completed that
water was admitted in the latter part of August and navigation was
opened on the first day of September, 1840. On that day the first
packet boat passed up the canal from Rochester to Mount Morris and a
daily line of packets then began this trip. Numerous warehouses were
erected along the line of the canal and freight boats were engaged in
the transportation of produce and merchandise. A collector’s office
was established at Scottsville and from then until the close of the
season $6,929.15 was collected in tolls.
In the fall of 1841 the canal was opened from Mount Morris to the
junction at Shaker settlement, 5.22 miles, and the branch from thence
to Dansville, 11.12 miles, thereby giving fifty-two miles of finished
canal. In April, 1842, a collector’s office was established at
Dansville and a collector appointed. The portion of the canal, from
Dansville to the Genesee river, which was completed, was supplied
with water from the Canaseraga and Mill creeks. In April, 1840, an
additional appropriation of $500,000 had been granted to carry on the
work of the Genesee Valley canal, and by an act (chapter 194) passed
May 18, 1841, the canal commissioners were authorized to borrow, on
the credit of the State, $550,000 to be applied toward the
construction of the canal.
The financial panic of 1837 had so disturbed monetary affairs that
the work of enlarging the Erie, building the Black River and Genesee
Valley canals, and repairing the other canals was prosecuted under
considerable embarrassment till the passage of what is popularly
known as the "Stop law." On March 29, 1842, this act (chapter 114)
was passed for the professed purpose of "paying the debt and
preserving the credit of the State." It ordered the suspension of all
expenditures on public works at that time in progress of
construction, except such as were necessary for the protection of
work already done. This act practically stopped all work on the
canals of the state, and contracts already let were stopped abruptly.
From this time till the new Constitution allowed further
appropriations there is little of interest to record. In March, 1843,
it was estimated that the total cost of the Genesee Valley canal
would be $4,535,776.47 and work to the amount of $4,224,700.88 was
then under contract. During the summer of 1843 practically no work
was done on the canal beyond that absolutely essential in the line of
repairs. During this season navigation was more or less interrupted
on the Dansville branch from the inadequacy of the water-supply.
Another obstruction to navigation during the early part of the season
was experienced in consequence of large accumulations of deposits
above the dam across the Genesee river near Mount Morris. It was
originally intended to cross the river at this point by means of an
aqueduct, and the contract was let and well under way, when in 1839,
under an act respecting the Genesee Valley canal, passed May 1, 1839,
the aqueduct was dispensed with by the acting commissioner then in
charge, who was of the impression that he was thereby cutting down
expenses, and a plan of locking boats to the pool above an existing
dam was adopted. The aqueduct would have been very expensive, but a
channel had to be dredged above the dam to allow boats to cross the
pool, and nearly four thousand cubic yards of accumulated earth had
to be taken out annually. If all the difficulties of maintaining good
navigation through the pond could have been foreseen, it is probable
that the original plan would have been carried out and the aqueduct
constructed.
The citizens of Dansville were dissatisfied with the terminal
facilities that had been supplied for them, and after having applied
in vain to the canal board and the canal commissioners for the
construction of a slip or for permission to construct a slip from the
village of Dansville and connect it with the side-cut, they proceeded
to construct a slip and basin and applied to the Legislature in 1844
for permission to connect them with the side-cut. Several
remonstrances were also presented to the Legislature against building
or assuming this work as a State charge.
After a bill for this purpose had been defeated the people of
Dansville were greatly aroused and one evening at dusk more than a
hundred of them assembled on the bank of the canal. One of their
number who was a large property owner mounted a pile of lumber and
made an incendiary speech to the people, describing the manner in
which the bill was defeated; he said to the crowd that they "were the
sovereign people, and their rights had been trampled on, and they
must do as their forefathers did to resist oppression, obtain their
rights (as he called them) by their own power." 4 On the following
morning they reassembled and cut through the berme bank and let the
water into the new side-cut, after using force to eject the State
employees from the village. Indictments were secured against the
ringleaders of this mob and they were all punished.
At the next session of the Legislature another bill authorizing the
builders of the side-cut to connect with the Dansville branch of the
Genesee Valley canal was defeated on the ground that its passage
would sanction a violation of law.
Not until 1848 (chapter 172) was the canal board authorized to assume
the Dansville slip and basin as a part of the Dansville branch of the
Genesee Valley canal. The main objection to this slip was the fact
that even without it the supply of water was inadequate and it would
require a great deal of water from the side-cut and could give none
in return. In accordance with this act the canal board assumed the
slip and basin on December 10, 1851, and they were thereafter
considered a part of the canal.
Some repairs were made to the canal in 1844-5. The banks were, to a
considerable extent, composed of material easily affected by the
action of water and required much labor to keep them in repair.
By an act of May 12, 1846 (chapter 246), the commissioners of the
canal fund were authorized to pay to the canal commissioners $10,000
to be expended by them in protecting and preserving from decay the
unfinished works and in the preservation of materials collected for
construction. A large amount of this fund was spent for transporting
materials from the unfinished to the finished portion of the canal
near the Shaker settlement, to be used in repairs or to be otherwise
disposed of. Although operations had been stopped, for the most part,
for over four years the work was standing well. The unfinished
portion extended from the junction at Shaker settlement to Olean, a
distance of sixty-six and a half miles, in which there were ninety-
five lift-locks, the foundations of seventy-one of which had been laid.
On January 1, 1847, the new State Constitution went into effect; this
permitted appropriations for the canals under article 7, section 3,
which reads as follows: "After paying the said expenses of
superintendence and repairs of the canals, and the sums appropriated
by the first and second sections of this Article, there shall be paid
out of the surplus revenues of the canals, to the Treasury of the
State, on or before the thirtieth day of September in each year, for
the use and benefit of the General Fund, such sum, not exceeding two
hundred thousand dollars, as may be required to defray the necessary
expenses of the State, and the remainder of the revenues of the said
canals, shall, in each fiscal year, be applied in such manner as the
Legislature shall direct to the completion of the Erie Canal
enlargement and the Genesee Valley and Black River canals, until the
said canals shall be completed."
From the time of resuming work till the opening of the entire canal
in 1862 the record shows a continuous succession of small
appropriations. The first of these was made by the act of May 12,
1847, (chapter 263) by which $128,000 was appropriated towards the
construction of the Genesee Valley canal. In pursuance of this act
contracts were let for finishing section No. 54, known as the "Deep
Cut;" for finishing the Portage tunnel, ten hundred and eighty-two
feet in length, and some smaller pieces of work. By an act of 1847
(chapter 446) a further appropriation of $50,000 was made and this
enabled the commissioners to let the contract for the completion of
the foundations and masonry of the Portage aqueduct and several locks.
About this time it was found that the Genesee Valley and Erie canals
were taking so much water from the Genesee river as to greatly damage
the water-privileges of the many manufacturing interests located on
the river, in and below Rochester. The Legislature took action
immediately, and after several methods of augmenting the supply of
water in the river were examined, they decided that making a
reservoir of Conesus lake was the most feasible plan, and by an act
of April 12, 1848, (chapter 339) they authorized the canal
commissioners to construct the works necessary for this purpose.
The Legislature appropriated the sum of $218,000 on April 10, 1848,
(chapter 217) to be applied to the construction of the canal, between
the navigable canal at Mount Morris and the Genesee feeder at or near
Caneadea. The contract for the completion of the Portage tunnel was
abandoned by the contractors with the consent of the commissioner in
charge, in September, 1848, and a new contract for an "open cut" in
place of the tunnel was awarded, thereby directly saving over $72,000
to the State, and indirectly a large amount, as a tunnel would
require very large expenditures to keep it in repair.
In 1849 that section of the canal from Mount Morris to the Caneadea
feeder, thirty-six and one-half miles, was all in progress of
construction. This entire distance was to be supplied with water from
the Genesee river at Caneadea and from the Wiscoy creek. On the
remaining portion from Caneadea to Olean (thirty-two miles), a large
amount of work was done previous to the suspension of work in 1842.
From previous experience with stone found in this vicinity, it was
found that it would not withstand the action of the atmosphere and
frosts, therefore the canal commissioners changed the plans,
specifying wood instead of masonry locks, thereby reducing the cost
$38,500.
On April 5, 1849, (chapter 227) the $128,000 appropriated in 1847
(chapter 263), or as much as remained unexpended, was reappropriated
and in addition $120,000 was appropriated (chapter 229), to be
applied between the navigable canal at Mount Morris and the Genesee
feeder at or near Caneadea, and $20,000 to the Ischua reservoir. In
the following year an appropriation of $170,000 was made (chapter
192), to be expended on the construction of the canal.
In the spring of 1851 thirty-six miles of canal extending from the
Shaker settlement, four miles above Mount Morris to the Genesee river
feeder, near the village of Rounesville, were opened. This made
eighty-eight miles of completed canal and left thirty miles partially
finished. Work on this last section was going on rapidly. The
Rockville reservoir and the Ischua feeder were commenced in 1839 and
1840. Millions of feet of lumber and staves, besides timber, shingles
and other produce were transported over the new portion of the canal
during the season of 1851.
Most of the supply of water required for the canal between Oramel and
Olean was to be furnished from Oil and Ischua creek feeders and
reservoirs, the estimated cost of which was $133,400. These were the
most important and expensive works yet to be constructed and it was
necessary that they should be started soon, as their completion was
essential to the opening of the last thirty miles of the canal.
In 1853 (chapter 620), $100,000 was appropriated towards the
completion of the Genesee Valley canal. In the following year
(chapter 329) an additional sum of $65,000 was allotted to this
canal. In 1854 (chapter 331), in response to petitions for a
navigable feeder for the Genesee Valley canal from the Genesee river
at Wellsville to intersect the canal at or near Belfast, the
Legislature instructed the canal board to prepare maps, plans and
estimates for this feeder. In March, 1855, the canal board reported
unfavorably on this project.
In the spring of 1856 an act was passed (chapter 149), directing "the
state engineer and surveyor and canal commissioners . . . to cause
surveys to be made for extending the Genesee Valley canal, from or
near the first lock north-east of the village of Olean, across and
through the bottom lands lying between said lock and the Alleghany
river, to the pond in said river known as the Millgrove pond, and to
make the necessary plans and estimates of the cost of the
construction of said canal, by the route and to the point aforesaid." 5
At this session of the Legislature only $32,000 was appropriated for
the Genesee Valley canal (chapter 148). At the next session, April,
1857, an act was passed (chapter 247), authorizing the extension of
the canal as contemplated by the act of 1856 (chapter 149), provided
the total cost could be kept under $109,000. By chapter 365 there was
appropriated $63,142.36 towards the completion and extension of this
canal, and in the next year (1858) $40,000 was apportioned for the
canal proper, and $61,212.36 for the extension.
In the spring of 1856 all work on the main canal was under contract
and rapidly nearing completion and the contract for the Oil creek
reservoir, which was to supply the deficiency of water experienced
during the dry part of the season, had at last been let, and was in a
fair state of progress. Two miles of canal from Oramel to Belfast had
been opened in 1853, and in 1854 three miles more, extending from
Belfast to Rockville, were completed and brought into use, making
ninety-three miles of completed canal. That section from Rockville to
Olean (twenty-four miles) was completed in the season of 1857, thus
making one hundred and seventeen miles of completed canal. During the
first season the only sources of water-supply for that portion of the
canal south of Rockville were the natural flow of Black, Oil,
Chamberlain and Ischua creeks, as the Oil creek reservoir was not
completed until 1858. In consequence of the leaky condition of the
banks and the scarcity of water, the canal below Hinsdale could not
be filled and it was found necessary to construct a feeder five rods
in length from Olean creek to the canal.
In November, 1857, the work for the construction of the extension of
the Genesee Valley canal from Olean nearly seven miles up the valley
of the Allegheny river to Millgrove pond was put under contract.
About six miles of this canal was completed and brought into use in
August, 1859. The rest of this work was so situated that it could not
be done advantageously except in time of low water. This extension of
6.70 miles would, when completed, connect the Genesee Valley canal
with the Allegheny river; and by a navigation of twelve miles on that
river, and a projected railroad of about twenty miles, it would
connect with coal mines said to be of great value and of almost
inexhaustible supply, and also with very extensive timber tracts.
Although one of the objects of constructing the Genesee Valley canal
was to connect with the Allegheny river at Olean, that object was not
then accomplished. To connect with the river at this point would
involve the construction of two locks, originally estimated to cost
$23,220. At this time it was thought that the construction of these
locks might be desirable but that their completion was not then
demanded. Neither the State of Pennsylvania nor the United States
Government had carried out their alleged plans of improving the
Allegheny river, so that the original scheme of drawing trade from
the Ohio and the other great rivers, to which its waters afforded
access, was destroyed. Pennsylvania did not wish to further New
York’s interests in this way, for she now had means of transporting
goods from Pittsburg to the coast without permitting any other State
to reap the advantages of their transportation.
The Buffalo, Bradford and Pittsburg railroad was then being
exploited. This railroad was to cross the Allegheny river about
fifteen miles below Olean, and it was claimed that its construction
would bring for transshipment to the river and thence to the canal,
coal and lumber in sufficient quantities to warrant the expenditure
necessary for the construction of the locks and the improvement of
the river. In 1859 (chapter 149) $17,700 was appropriated for the
completion of the canal and extension. This was followed in 1860
(chapter 213) and 1862 (chapter 137) by appropriations of $56,840 and
$8,000, respectively.
In December, 1861, the extension of the Genesee Valley canal was
completed and brought into use on the opening of navigation in 1862.
This completed the construction of the canal and the accounts were
closed. The lockage from Rochester to the summit level in Allegany
county was all ascending, as was also that by the branch to Dansville
in Livingston county. The summit extended from New Hudson to North
Hinsdale, a distance of about twelve miles, thence the canal
descended to the Allegheny river.
The provisions made for supplying the canal with water were as
follows: proceeding southerly from the Erie canal, there were: first,
a feeder from Allen’s creek at Scottsville; second, the Genesee
river, one mile north of Mount Morris; third, a feeder from Wiscoy
creek at Mixville Landing; fourth, a feeder from the Genesee river at
Oramel; fifth, Rockville reservoir at Rockville; sixth, a feeder from
Oil creek reservoir, two miles north of Cuba; seventh and eighth,
Champlain and Chamberlain’s creeks, in the village of Cuba; and
ninth, a feeder from Ischua creek near Hinsdale. The last four
feeders entered the canal on the summit level. South of the summit at
Smith Mills there was a short feeder from Olean creek. The Dansville
branch was supplied by a feeder from Mill creek at Dansville and one
from the Canaseraga, two miles north of that place. The supply for
the branch was not quite sufficient during the dry season, but that
of the main line was ample for the needs of that time if properly
husbanded. Of all these feeders and reservoirs the Oil creek
reservoir was by far the most important. Its flow line, when full,
covered about four hundred and seventy acres and its average depth
was estimated at twenty-five feet. At the dam it was forty-six feet
in depth. The embankment forming the dam was two thousand feet in
length, fifty-six feet in height and two hundred and ninety feet in
breadth at the base where it crossed the channel of the creek.
The locks of the canal were of three kinds: wooden, composite and
stone. The wooden locks were used on account of the poor quality of
the stone of that region and the great expense of bringing stone
there before the canal was opened. It was intended to rebuild these
with stone as soon as the canal could be used as the means of
transporting the material.
In April, 1863, an act was passed (chapter 342) authorizing the canal
commissioners to raise the water in Oil creek reservoir three feet,
also to build a dam across Ischua creek at Ischua feeder at such
elevation as might be determined by the canal board and to raise and
maintain, at an elevation of five feet above the bottom of the canal,
the dams across the streams that supplied with water that part of the
canal designated as the extension of the Genesee Valley canal.
It was difficult to meet the ever increasing demand for more
reservoirs, caused by the growing business of the canal, and in 1864
(chapter 170) the Legislature appropriated $85,000 towards making a
reservoir of Lime lake and towards rebuilding with rubble masonry
five locks. In 1866 (chapter 304) the balance of the 1864 allowance
was reappropriated and the further sum of $6,936.26 was added to it
for the original purpose of the act of 1864. The locks were completed
and brought into use during the following season.
Owing to the nature of the country, either with its many streams
flowing into the canal or with the canal following their winding
courses through the narrow valleys, the Genesee Valley canal was
bound to require large expenditures for maintenance and repair. It
was a country of floods; the outlets of the valleys could not take
care of their great drainage areas and the floods frequently washed
out canal embankments and carried away dams, locks and aqueducts.
On May 7, 1868, an act was passed (chapter 715) appropriating the sum
of $242,000 for furnishing additional water to the summit level of
the Genesee Valley canal, improving Ischua feeder, changing the plan
of rebuilding Ischua feeder aqueduct, removing Mud lock, deepening
and widening the channel of the Genesee Valley canal, from the guard-
lock at the rapids to the junction with the Erie canal, for
protecting the canal at the "slide banks" and for improving the canal
in general.
After careful investigation it was decided that the best way of
increasing the supply of water for the summit level was to raise the
surface of Oil creek reservoir six feet (covering an area of about
five hundred and twenty-five acres) and to construct a new reservoir
on the Ischua creek by raising a dam about twenty-five feet in
height, and thus flooding some two hundred acres. It was estimated
that these improvements would furnish a supply of water sufficient
for the lockage of twenty-seven boats per day in each direction
through the entire season and that this would meet all demands for
many years to come. But in 1869 the canal commissioners decided that,
as the proposed reservoir of Ischua creek would flood the best
farming lands of that section, it would be cheaper to raise the State
dam across the Ischua creek about six and one-half feet and to
increase the capacity of Oil creek reservoir by raising the dam there
an additional two feet.
On May 12, 1869 (chapter 877), the Legislature set aside $50,000 for
protecting the slide banks and otherwise improving the Genesee Valley
canal. In the following year (chapter 767) $100,000 was allotted to
the Genesee Valley canal for improvements and for completing work
already under contract. In 1871 the Legislature (chapter 930)
appropriated $13,000 for constructing a stone abutment and docking at
the east end of the dam across the Genesee river at Mount Morris and
$12,000 to pay for work at that time under contract and for
protecting the Genesee Valley canal against the encroachments of the
Genesee river.
On May 23, 1872 (chapter 850), the Legislature made provision for
increasing the water-supply at the Dansville end of the Dansville
side-cut. An appropriation of $10,000 was made for conveying the
water from Loon lake into the canal at Dansville by discharging it
through Mill creek. Loon lake was about ten miles from Dansville; it
was about one mile long and one-third of a mile wide, and by opening
a channel about one-quarter mile in length the water would pass down
natural watercourses to Mill creek above the point where that stream
entered the side-cut. The contracts for deepening the summit level
and for raising the dam of Oil creek reservoir were completed during
the season of 1872. In 1873 the Legislature appropriated $18,537.94
for the canal (chapter 643) and in the following year (chapter 399)
$2,000 was set apart for raising the tow-path bank on the four and
six-mile levels to prevent flood waters of the Genesee river from
overflowing.
There was considerable delay in the opening of navigation in the
spring of 1874, occasioned by an extraordinarily high freshet. At
first it was supposed that the damage which the canal had sustained
was so great that the State would not be warranted in attempting to
put it in repair. The dam was carried out at Shaker’s, together with
much embankment both there and along the Cuba level. It was finally
decided to make temporary repairs and navigation was opened about the
first of June.
Shortly before this time the public mind began to be agitated on the
subject of abandoning some of the lateral canals, but as another
chapter has been devoted to a study of the causes that led to this
condition it is not needful here to repeat the deductions from that
study, but simply to state a few of the facts as they related to the
Genesee Valley canal.
At the fall election of 1874 the State Constitution (article 7,
section 6) was so amended as to "give the Legislature the authority
to sell, lease or otherwise dispose of" any of the canals of the
State, except the Erie, Champlain, Oswego and the Cayuga and Seneca
canals. As it could not have been supposed possible to "sell or
lease" the other lateral canals which were not paying financially, on
conditions which required the purchaser to maintain and operate them,
this amounted to abandonment, should the Legislature decide to
dispose of them.
By an act of 1875 (chapter 499) the Legislature required the canal
board to investigate and report upon the disposition to be made of
the lateral canals; to take testimony and examine maps, surveys and
documents relating to the same; to ascertain whether they should be
sold, leased or abandoned; whether any should be retained as feeders
and as to what effect such sale, lease or abandonment would have upon
the legal rights of individuals.
According to the report of the canal board the Genesee Valley canal
had cost in the aggregate $6,723,625.23, with some claims against the
State on file in the appraisers’ office. They recommended that the
State should lease the canal for a term of years or should sell it
outright on condition that it should be maintained in good condition
for four or five months each year. If it were impossible to either
sell or lease the canal, they advised that the State should abandon
the canal at the end of three or five years.
In May, 1876, a commission of three citizens of the State, – Warner
Miller of Herkimer county, E. W. Chamberlain of Allegany county and
Artemus B. Waldo of Essex county – was appointed by the Legislature
(chapter 382) to further investigate the advisability of abandoning
the lateral canals. An appropriation of $40,000 was made at the same
time (chapter 386) to defray the expenses of collecting tolls,
superintendence and maintenance for the year.
These commissioners reported that many of the structures on this
canal were in a condition to last for two or three years with slight
repairs, but some of them would need extensive repairing to fit them
for another season’s service; that the amount of tolls collected
during the season of 1876 was $14,668.50, the amount of tolls
contributed to the Erie canal was only $513 and the expenditures for
repairs and employees amounted to $23,264.10; that the expenses for
operating the canal during a season of three or four months in 1877,
if no unusual break occurred, need not exceed those of 1876; that the
reservoirs and feeders along the line of the canal were not required
to supply the Erie; that ample facilities for transportation were
furnished by the adjoining railroads and that these roads had already
superseded the canal in the carrying of nearly all the trade and
tonnage of the country, except in the article of lumber. Therefore,
they advised that it should be opened for at least a part of the
season of 1877, that the lumber products stored along the route might
be shipped, and that then the canal should be abandoned. They
recommended that the Dansville branch should be closed immediately
(January 19, 1877).
By an act of June 4, 1877 (chapter 404), the Legislature directed
that the Genesee Valley canal should be abandoned and discontinued as
a canal and be no longer subject to the control or authority of any
of the canal boards or officers of the State on or after the
thirtieth day of September, 1878. The act also directed that it
should be the duty of the canal commissioners or Superintendent of
Public Works, subject to the approval of the canal board, as soon as
practicable after the close of navigation in the year 1878, to
advertise for sale and to sell the Genesee Valley canal, its feeders,
branches, appurtenances and water-privileges. On June 18, 1879
(chapter 522), this act was amended and the date for selling the
canal was changed to January 1, 1880.
In 1880 the division engineer of the western division reported the
need of retaining the Cuba and other reservoirs of the abandoned
Genesee Valley canal as feeders for the Erie canal. Under chapter
326, Laws of 1880, the Legislature authorized the commissioners of
the land office to sell the banks and prism of the Genesee Valley
canal for $100 per mile to any railroad corporation that would give
bonds as a guarantee that it would, within two years, begin the
construction of a standard gauge railroad substantially following the
line of the Genesee Valley canal. This act reserved two sections of
the canal property – from Allen’s creek feeder to Rochester and from
Cuba reservoir to Rockville reservoir.
On November 6, 1880, the Governor deeded the main line of the Genesee
Valley canal to the Genesee Valley Canal Railway Company, so that,
with the exception of the Cuba reservoir, its feeder of about three-
fourths of a mile between the reservoir and the Genesee Valley canal,
about seven and a half miles of canal below the mouth of the feeder
and about ten miles between the dam across Allen’s creek and the City
of Rochester, the Genesee Valley canal was no longer under the
control of the State. These portions were retained for the purpose of
feeding the eastern end of the "long level" of the Erie canal in the
City of Rochester.
By an act of 1882 (chapter 166) the State sold the Dansville side-cut
and the Wiscoy and Ischua reservoirs and feeders to farmers whose
lands abutted on these sections of the canal and feeders.
This canal with its numerous structures, costly in their original
construction and not less so in their maintenance, was built after
the era of canal-building had substantially ended. The locomotive,
and consequently the method of transportation by railway, had just
come into use and was practically tested when the construction of the
Genesee Valley canal was entered upon. The Erie railroad was
completed and in operation when the last section of the canal was
brought into use at Olean.
The expectations of the projectors of this canal, as they related to
its business and its pecuniary importance to the country, were never
realized. The Genesee Valley canal, like the other laterals, probably
did not, in the way of tolls received, pay more than one-quarter the
cost of repairs, but it saved over $150,000 annually to the people of
the City of Rochester in the reduced price of lumber. The measure of
its utility was out of all proportions to its cost, but there is
reason to wonder whether the agricultural wealth it created, the
industries it stimulated, encouraged and established, the thousands
of benefits and conveniences which it yearly conferred, directly and
indirectly, on the country through which it passed and at its
termini, were not so vast in the aggregate as to counterbalance to a
large extent the expenditures that the State had made.
------------------------------
ENDNOTES.
1 Assembly Journal, 1825, p. 612.
2 Laws of 1825, p. 356. (chapter 236.)
3 Laws of 1836, p. 340.
4 Senate Documents, 1845, No. 96.
5 Laws of 1856, p. 243.
----------------------------------------=
|